Geothermal System Installed at Goddard's Building 25
by Chip Wellington for Goddard Space Flight Center
Greenbelt, MD (SPX) Aug 03, 2012


File image.

NASA's Goddard Space Flight Center is pleased to announce the start-up of a new geothermal system for Building 25's Network Testing and Training Facility. The new system has been turned on, and will provide heating and cooling with a geothermal HVAC (heating, ventilation, and air conditioning) system.

The newly installed system began initial operations on May 30, 2012 and will provide the building with up to 2.6 million BTUH of heating. The speed of the movement of heat is called the heat loss and is measured in BTUH, which means BTUs (British Thermal Units) per hour.

The system will also supply 280 tons (3.4 million Btuh) of cooling; approximately enough heating and cooling for 90 homes (based on 3 tons of cooling per home).

This renewable energy solution was installed to avoid the replacement costs of aging steam and chilled water lines and demonstrates the feasibility to retrofit a medium sized building with this technology with minimal disruption to the building occupants.

The newly installed geothermal system contains 100 wells drilled to a depth of 400 feet per well. The ground water is recirculated in a closed loop system through the well field and into the building's newly installed water to water heat transfer pump.

The water to water heat transfer pump has eight modules capable of meeting both heating and cooling requirements automatically by assigning individual modules in either heating or cooling mode.

The geothermal system installation cost was the same cost as the replacement of steam, condensate and chilled water lines that required replacement.

The cost avoidance is projected to be $34,138 annually, which is a 15 percent reduction from the current annual energy costs for Building 25.

Additionally, the Central Plant will experience improved efficiency because it will no longer have to supply heating and cooling to Building 25, which was the furthest point from the plant.

The project started in May 2011 and is scheduled for completion in September 2012. The project is managed by NASA Goddard's Facilities Division.

.


Related Links
Goddard Space Flight Center
Powering The World in the 21st Century at Energy-Daily.com






Comment on this article via your Facebook, Yahoo, AOL, Hotmail login.

Share this article via these popular social media networks
del.icio.usdel.icio.us DiggDigg RedditReddit GoogleGoogle








ENERGY TECH
New method to encourage virtual power plants for efficient renewable energy production
Southampton UK (SPX) Jul 31, 2012
Researchers from the University of Southampton have devised a novel method for forming virtual power plants to provide renewable energy production in the UK. In the last decade, small and distributed energy resources (DERs), like wind farms and solar panels, have begun to appear in greater numbers in the electricity supply network (Grid). To ensure that energy demand is met without interru ... read more


ENERGY TECH
UCLA research makes possible rapid assessment of plant drought tolerance

Parched fields as drought devastates US crops

Public strongly supports programs helping farmers adapt to climate change

Study: All chickens have Asian roots

ENERGY TECH
How to avoid traps in plastic electronics

HP claims win in legal battle with Oracle

Japan's Toshiba falls into quarterly net loss

World's smallest semiconductor laser created by University of Texas scientists

ENERGY TECH
Japan's ANA posts small Q1 net profit, reversing loss

Boeing 737 Performance Improvement Package Delivers on Promise to Cut Fuel Burn

Australia's Hawk jets reach 75,000 hours

US, allies renew opposition to EU airline tax

ENERGY TECH
Poll: Many think in-car technology a risk

Toyota says quarterly profit skyrockets to $3.71 bn

Pedestrianised Left Bank could spell Paris logjam: report

Toyota recalls 600,000 vehicles in Europe

ENERGY TECH
Kenyans weigh cost of Chinese investment

Paraguay row set to weaken Mercosur pact

Australian opposition wants more foreign investment scrutiny

Big cash stockpile puts US tech firms on the spot

ENERGY TECH
Turkmenistan to plant huge forest in Aral Sea region

Taking Stock Of Georgia State Forests

Tropical arks reach tipping point

Forest carbon monitoring breakthrough in Colombia

ENERGY TECH
France orders Google to hand over Street View data

Space Technologies Tackle Human and Environmental Security Problems

Chinese mapping satellite handed over to surveying authority

European data center for GMES Sentinel satellites at DLR

ENERGY TECH
Cutting the graphene cake

A giant step in a miniature world

A new era in modern analytical chemistry with Nano-FTIR

Entropy can lead to order, paving the route to nanostructures




The content herein, unless otherwise known to be public domain, are Copyright 1995-2014 - Space Media Network. AFP, UPI and IANS news wire stories are copyright Agence France-Presse, United Press International and Indo-Asia News Service. ESA Portal Reports are copyright European Space Agency. All NASA sourced material is public domain. Additional copyrights may apply in whole or part to other bona fide parties. Advertising does not imply endorsement,agreement or approval of any opinions, statements or information provided by Space Media Network on any Web page published or hosted by Space Media Network. Privacy Statement