General Atomics (GA) has begun long-term reliability testing of the full-scale power train of the Electromagnetic Aircraft Launch System (EMALS) in its new 5,000 square foot high cycle test (HCT) facility at its Tupelo, Mississippi assembly plant. This test program will yield overall reduced technical risk, demonstrate EMALS system performance and meet contract specification requirements.

The purpose of this work is to more thoroughly test the EMALS system intended for installation on CVN-78. This effort focuses on determining those tests that would maximize technical and operational risk reduction to the EMALS program.

Examples of tests include extended single power train testing, expanded tests of critical safety items and critical application items, as well as more expansion control system testing than originally planned on the SDD program.

The 5,000 square foot HCT facility has more than 4 megavolt amperes (MVA) available to provide power to a high-speed rotating energy storage system. More than 2 million BTU/hr of freshwater cooling can be controlled to represent the highest seawater temperatures that the EMALS equipment is designed for.

Up to three multi-megawatt rectifiers and three electronic power inverters can be tested. The facility also can test a complete 12-foot EMALS linear motor module.

The HCT facility is now testing the EMALS rotating energy storage system by pulsing the system to simulate aircraft launches at a rate of over 250 launches per day.

"This testing will provide even greater assurance of the success of the EMALS system prior to installation on the CVN-78 carrier," says General Atomics Aircraft Launch and Recovery Equipment (ALRE) program director, Susan Wojtowicz. The testing is conducted at a separate, dedicated facility adjacent to the GA Electromagnetic Systems Tupelo Manufacturing Facility (EMS TMF).

According to EMS TMF General Manager Pete Rinaldi "qualification testing is being conducted without impacting current linear induction motor manufacture and inverter assembly. We are currently completing 250 Megawatts (MW) of motor manufacture and associated motor inverter manufacturer. We plan on manufacturing 1,000 MW of motors in the next few years. In addition, during this same time period, we plan on manufacturing 1,500 MW of motor inverters. The test facility will enable ongoing and future qualification of high power electrical equipment without impact to our manufacturing operations."

Related Links
General Atomics
Naval Warfare in the 21st Century



Memory Foam Mattress Review
Newsletters :: SpaceDaily :: SpaceWar :: TerraDaily :: Energy Daily
XML Feeds :: Space News :: Earth News :: War News :: Solar Energy News


Outside View: India's new sub -- Part 2
Moscow (UPI) Jul 18, 2008
When the Indian government raised the issue of leasing a nuclear submarine from Russia, it focused negotiations on a multirole SSN, Project 971 Shchuka-B, known in the West as Akula, then under construction in the Far Eastern Russian city of Komsomolsk-on-Amur. (United Press International's "Outside View" commentaries are written by outside contributors who specialize in a variety of important issues. The views expressed do not necessarily reflect those of United Press International. In the interests of creating an open forum, original submissions are invited.)







  • China Southern Airlines managers take paycut due to oil prices
  • British PM blasts polluting 'ghost' flights
  • Air China says it is to buy 45 Boeing aircraft
  • Raytheon Leads Team To Evaluate Impact Of New Classes Of Aircraft For NASA

  • China loses WTO car parts case against US
  • Off-peak electricity could power hybrids
  • Lasers, Software And The Devil's Slide
  • Future Of Transit Taking Shape At The Big Blue Bus

  • DRS Completes Testing Of PMM System
  • Boeing To Demo Net-Centric Upgrade On AWACS Aircraft
  • Satellite's Instrumentation Providing Scintillation Forecast Data
  • USAF E-8C Joint STARS Airframes Operationally Viable Through 2070

  • BMD Focus: Poles block base -- Part 2
  • BMD Watch: PAC upgrade orders for Raytheon
  • US missile defense test delayed until December
  • Russian opposition to missile defense unjustified: US general

  • UN chief calls for sharp hike in world farm output
  • Pollination Habits Of Endangered Rice Revealed To Help Preservation
  • Digital Cameras And Remote Satellites Measure Crop Water Demand
  • Brazil agribusiness wants looser ties to China, India in WTO talks

  • Thousands evacuated as storm hits China: state media
  • China quake zone govt to sell luxury HQ after outcry: report
  • China quake sends 1.4 million back into poverty: report
  • Asia sets stage for disaster relief exercise with key powers

  • Advertisers' dream as Japanese display identifies customers
  • Virtual World Is Sign Of Future For Scientists And Engineers
  • Satellite Users Group Opposes UTC Request
  • EchoStar XI Satellite Deploys Solar Arrays On Schedule

  • NASA Robots Perform Well During Arctic Ice Deployment Testing
  • Eight Teams Taking Up ESA's Lunar Robotics Challenge
  • Three Engineers, Hundreds of Robots, One Warehouse
  • Tartalo The Robot Is Knocking On Your Door

  • The content herein, unless otherwise known to be public domain, are Copyright Space.TV Corporation. AFP and UPI Wire Stories are copyright Agence France-Presse and United Press International. ESA Portal Reports are copyright European Space Agency. All NASA sourced material is public domain. Additional copyrights may apply in whole or part to other bona fide parties. Advertising does not imply endorsement, agreement or approval of any opinions, statements or information provided by Space.TV Corp on any Web page published or hosted by Space.TV Corp. Privacy Statement